BUSINESS PROCESS MANAGEMENT GOES BALISTIC
The Royal Navy streamlines complex procurement process
By Howard Mathers, Team Leader, Submarine Integrated
Project Team, Warship Support Agency, part of the Ministry of Defence,
Mike Owens, Director of Submarines, Devonport Management Limited, Andy
Cooper, SDE Project Manager, Devonport Management Limited, and John
Stewart, Senior Consultant, Staffware Plc.
1. Introduction
The peace dividend in the 90s resulted in a reduction in the Royal Navy’s
submarine fleet, with the complete phasing out of conventional submarines
by 1994. Today, the Navy’s entire submarine fleet is nuclear powered,
and the role these vessels play has been enlarged. Following the 1998 Strategic
Defence Review, the nuclear-capable Trident submarines have a far more
flexible role with tasks that include trials, surveys and exercises. The
Royal Navy has four Trident submarines in the Vanguard class, with a further
seven hunter/killer submarines in each of the Swiftsure and Trafalgar classes.
The
first of the Trident submarines, HMS Vanguard, is currently undergoing
its first refit, called a Long Overhaul Period (Refuelling) (LOP). Undertaken
periodically and costing many hundreds of millions of pounds, the overhaul
of a modern nuclear submarine is a very complex process involving a large
number of geographically diverse parties, at a number of levels from
the vessel’s staff, the dockyard, to various consultants and contractors,
right up through to the Warships Support Agency, a part of the Ministry
of Defence.
2. Overview
The refurbishment of a nuclear submarine is a major exercise involving
refuelling the nuclear reactors, extensive safety checks and surveys,
refurbishing systems, replacing equipment and implementing capability
upgrades.
The Ministry of Defence (MoD) issues a specification for an overhaul one
to two years in advance so that by the time the submarine enters dry-dock,
the extent and detail of the works has been understood, as well as the
complex procurement processes actioned – many replacement components
are not stock items.
Apart from the MoD Submarine Support Integrated Project Team (SubIPT),
which is part of the Warship Support Agency, there are a number of other
organisations involved in the overhaul: Devonport Royal Dockyard, where
the vessel is to be dry-docked for the overhaul (which is owned and operated
by Devonport Management Limited), Rolls Royce (the design authority and
main supplier of the nuclear plant on all Royal Navy nuclear submarines),
and various consultants and contractors, as well as the crew of the vessel
itself.
Due to the enormous complexity, when an overhaul specification is issued,
it results in a myriad of enquiries. These include requests for surveys
of various elements of the vessel for more information, or to determine
what work is needed, or whether a particular item needs replacement, refurbishment
or upgrading. There are thousands of such enquiries and each one needs
to be resolved. It is not unusual for the resolution to one query to impact
on numerous other elements within the vessel as many of the systems and
components are inter-related and inter-dependent.
This advance planning phase of the overhaul is also important as many
of the components used on a nuclear submarine are bespoke and as such have
very long procurement lead times – it is not as though a new nuclear
reactor safety system can be picked off the shelf and installed! Most parts
are tailor made and need to go through stringent procurement and testing
procedures.
Devonport Management Limited (DML), in partnership with WSA, decided that
the ‘first-of-class’ overhaul of HMS Vanguard would be an
ideal opportunity to review and upgrade the entire overhaul process.
3. Key motivations
A key theme in the WSA’s current policy is to reduce the overall
cost of ownership of large capital assets. An area of concern was the total
length of time and the cost to refurbish each nuclear submarine. An area
identified as being particularly relevant was the enquiry system, both
pre-overhaul and during the process. Enquiries were taking on average 15
days each to resolve, which was considered to be far too long.
The existing
system used to control and monitor the overhaul was largely paper-based,
although there was an element of electronic communication.
The legacy system was green-screen based and was very clumsy and had
to be augmented by paper records. There were some other computer systems
used
but they were self-contained and not web-based. The whole system needed
to be streamlined and updated, as such the project team has augmented
and improved the process and where possible reduced the total number of
systems
in use.
Other motivations running from the above were:
- A need for better interaction
between all the parties, which are geographically spread.
- A need for
better monitoring and management control of the entire system.
- A requirement
for more timely, accurate, and comprehensive information to be available
for all parties.
- A desire for continuity in the process.
- Pan-Enterprise visibility of
processes and progress
4. Business innovation and management impact
Project leaders
The two principal organisations involved in the whole overhaul project
were the Naval base, DML, and SubIPT, which is the team within the Warship
Support Agency responsible for the project.
Howard Mathers is the SubIPT team leader, based at MoD Abbey Wood, Bristol.
Mike Owen, is director of submarines for DML, Plymouth. Devonport Royal
Dockyard was a GoCo – Government-owned, contractor-operated organisation
until being privatised in 1997. The main shareholders are now Kellogg Brown & Root,
Balfour Beatty and the Weir Group.
Approach
Although a number of approaches were considered, it was decided that a
radical one would be tried. It was felt that tinkering with some elements
of the system would not produce the desired results, a fundamental change
was needed. The existing system had developed over some time, growing
as new needs and requirements emerged. Although critical paths were identified
and monitored, the idea of workflow was not a recognised concept when
this system evolved.
The overhaul of HMS Vanguard was scheduled to take place at Devonport,
starting in 2002. It was decided that this would be the first project to
introduce a new system, a sort of pilot to see just what could be achieved.
The process to be undertaken was far reaching: the whole project was to
be reviewed from the point of issuing the notice of overhaul, through the
pre-overhaul enquiry stage, through the overhaul itself to completion and
re-commissioning. This would ultimately be implemented at every level,
including the vessel itself, the dockyard and the other contractors. It
would change the way the parties worked together, the way they communicated,
the way the process was managed, and the way the parties were monitored,
and produce performance data which could be evaluated.
Mike Owen and Howard Mathers are the key decision-makers for the overhaul
of any Royal Navy submarine at Devonport. Other members of the team working
on HMS Vanguard included the Logistics Support Company (LSC Group - a specialist
logistics company and now a subsidiary of DML) and Rolls Royce (nuclear
propulsion plant).
The first phase of the implementation of the new approach was to fully
review all the stages and processes involved, prior to an actual overhaul
project. The whole overhaul system from the notice, through the enquiries,
to the overhaul specification and overhaul itself was analysed and scrutinised.
The entire process was mapped so that the various workflows could be identified
and quantified. This enabled the areas of the process to be identified
which could be re-engineered to be more efficient, augmented or replaced
by technology, or simply cut out as too bureaucratic.
LSC retained the services of Staffware, a UK-based specialist in business
process management, to assist in this process. John Stewart, a former military
man himself and a senior consultant, led the Staffware team.
The specification of the new system was a complicated process, involving
the creation of a series of new workflow procedures. This included the
re-engineering of certain elements of the business process, and allowed
a proportion of the process to be automated.
Although seeking fundamental overall change, the management team adopted
a cautious approach. Before each stage was authorised, the benefits in
terms of performance and efficiency had to be quantified. Even then, before
consolidating that stage and moving on to the next, it had to be working
properly, clearly demonstrating the required change in terms of pre-defined
key performance indicators (KPIs).
5. Technological innovation and process/procurement changes/improvements
There were a number of factors which usefully came together to allow the
SubIPT to consider a change of approach: the introduction of the Restricted
LAN Interconnect (RLI) providing an extensive Intranet system across the
entire service using standard desktop tools, the need to replace the existing
overhaul enquiry IT system and, most notably, the first-of-class overhaul
of a Trident submarine.
The Long Overhaul Programme (Refuelling)
The whole process starts with the issue of a notice by the SubIPT that
HMS Vanguard is to be overhauled. A Long overhaul period (Refuelling)(LOP)
draft specification document is produced which outlines the work to be
undertaken including upgrades, maintenance and repairs.
The overhaul specification identifies a significant number of surveys
to be undertaken which may lead to further work. During the planning phases
of the LOP specification the contractor will raise significant enquires
to clarify what is required, to suggest new innovative ways of working
or to identify conflicts with different aspects of the specification. The
volume of these enquires can be significant and is important to try to
clear these prior to the specification freeze as changes after this are
dealt with by the change/amendment processes (DAR) which can add significant
change management effort to all parties involved.
The final specification is issued to the contractor with an electronic
and paper copies of the specification are sent to the vessel and key overhaul
stakeholders. The contractor will produce a fully resourced LOP schedule
and submit a tender for the work identified in the specification. In many
cases this tender will have caveats/assumptions, which are to cover any
outstanding enquires.
Specification Change Instruction (SCI): the problem
The existing system was largely paper-based, augmented by an antiquated
RSCI (overhaul specification change instruction) system and a number of
stand-alone IT systems. The enquiries were written on the prescribed form
and then despatched through the hierarchy and a myriad of people who had
to see, make comment, approve and even answer the enquiry. There was no
way of monitoring the progress of the enquiry, knowing where it was, or
easily appreciating implications of any decisions made on other aspects
of the overhaul.
The other problem was that on many occasions the form did not have the
necessary information and had to be returned to the initiator for completion,
further delaying its resolution.
SCI’s: the solution
The enquiry system was identified as the cause of most of the delays in
the process, and the obvious priority area for change. It was decided to
digitise the whole system, making it workflow and web-based, through a
secure intranet. Staffware business process orchestration software was
used to ensure that the business process was achieved whilst ensuring full
audibility and delivering significant business benefits.
This was a significantly different way of working so stakeholder involvement
was critical. This was achieved through a series of regular end-user meetings
to enable participation at every stage from concept, through design to
implementation. This forum was also useful in coordinating training on
the new system.
This element went very smoothly as each stakeholder took ownership of
the new system and communicated the positive aspects of the new system
(change agents) to their representative area.
Familiarity with the existing system was seen as a huge benefit so the
new system was designed to replicate the old electronically, thus reducing
the need for too much change management. The electronic forms were designed
to be similar to those used previously, and largely followed the same routes.
Digitisation and application of workflow parameters resulted in a number
of problem areas being resolved almost instantly. The accuracy of information
improved significantly as all the data had to be entered completely otherwise
an enquiry could not be logged on to the system. The speed of answers to
enquiries improved, as distribution was instantaneous, and simultaneous
to all those parties that needed to be contacted. It introduced tracking
which enabled the management to see where bottlenecks were. It also enabled
any party to track an enquiry that had specific implications or was urgent.
Surveys: the problem
Surveys are required to ensure that the submarine is safe to remain in
service and to identify areas of the vessel that may require repair. The
potential impact result of surveys work can have on the LOP schedule and
the return of the submarine to active duty cannot be understated.
The LOP specification identifies what surveys are to be undertaken by
the contractor or sub-contractors. The old system was paper based and required
review by the contractor’s internal technical and commercial specialists
before progressing. This system suffered significant delays in processing,
excessive administrative controls (photocopying and tracking), and a lack
of real time visibility of the whole process.
Delays meant that in some cases recommended decisions were not authorised
until after a compartment or system was replaced resulting in rework and
additional cost.
Surveys: the solution
It was decided to digitise the whole system,
making it workflow and web-based, through the same secure Intranet as SCI’s.
Stakeholder involvement and regular workshops at key stages of the process
were again successfully
employed.
Familiarity with the existing system was seen as a huge benefit so the
new system was designed to replicate the old electronically, thus reducing
the need for too much change management. The electronic forms were designed
to be similar to those used previously, and largely followed the same routes.
The system also allowed for uploading of electronic attachments enabling
all instant access to digital photographs and other information required
for the decision making process.
Workflow has also linked to the DML production, estimating and planning
system, which triggers procurement, programming, working practices, testing,
safety, costing and certification procedures.
This system has enabled HMS Vanguard to process 16616 survey items over
a two year period whilst reducing administrative effort, Improving turnaround
timescales, ensuring audibility.
Concessions: the Problem
When surveying equipment’s during LOP there are times when equipment’s
are outside of design specification but fit for continued service. Traditionally
this has required applying for a concession/CNC/production permit (PP)
through an existing paper system. The paper application will be reviewed
internally by the contractor’s technical and commercial specialists
before being progressed.
Similar to the survey process the paper based system suffered significant
delays in processing, excessive administrative controls (photocopying and
tracking), lack of real time visibility of the whole process. Concessions/CNC’s/PP
raised on paper also had to be typed back into the Platform Configuration
Management system (SDD) without attachments. This meant that SDD users
could see the application but not the supplementary attachments.
Several concessions/CNC’s/PP were lost each refit and the average
time a concession was taking was 3 months leaving LOP’s at significant
risk until the application was granted.
Concessions: the Solution
It was decided to digitise the whole system,
making it workflow and web-based, through the same secure Intranet as SCI’s
and Surveys. Stakeholder involvement and regular workshops at key stages
of the process were again
successfully employed.
Familiarity with the existing system was seen as a huge benefit so the
new system was designed to replicate the old electronically, thus reducing
the need for too much change management. The electronic forms were designed
to be similar to those used previously, and largely followed the same routes.
The system also allowed for uploading of electronic attachments enabling
all instant access to digital photographs and other information required
for the decision making process.
The system is also linked to SDD which enabled the concession/CNC/PP to
be linked in SDD, removing the need for applications to be typed in by
a data processor.
This system has enabled HMS Vanguard to process 547 concessions for the
last year averaging since June 2003 29.9 days (319 applications raised)
to raise, process, sentence and close. The system has allowed KPI’s
to be produced straight from the system, reduced administrative effort
and ensured visibility/audibility.
Additional functionality
The system also provides a discussion forum.
Where lessons learnt or important informal messages can be posted in the
forum, and linked to specific enquiries,
surveys or concessions/CNC’s/PP. Others can then enter the discussion,
which uses a simple ‘chatroom’ format, with such postings being
automatically notified to the initiator.
6. Hurdles
There were a number of critical issues to overcome:
- There was resistance
to any change. It was important to involve the entire stakeholder community
in this change from the outset.
- Levels of computer literacy had to
be changed, although the introduction of the NavyNet required that
anyway.
- Integration of various systems and databases to make the new
process work. These were not only SubIPT and DML but also subcontractors
such as Rolls
Royce. This was overcome using business process management (BPM)
and business
process orchestration (BPO) software.
- Trust. Much of the business
process is invisible to the user. Early operation of the system would
also involve users checking via the telephone that
information was flowing to the correct place. This quickly stopped
as the
users became familiar with the operation of the system.
- Recognition
of the need to ‘Keep it Simple’, ensuring applications
were written to be easy and intuitive to use, even for those
with extremely limited IT background.
- Recognition of the need
for through life continuous improvement support for these new
business critical processes. The old style of IT project
management, whereby an application is delivered and the project
ends is unacceptable with these integrated systems. Funding
must enable key improvement
activities, especially training, to be supported throughout
the life of
the service.
7. System configuration
The introduction of NavyNet providing an extensive Intranet system across
the service using standard desktop tools, to some degree, facilitated
the introduction of the new workflow system. Defining exactly what additional
hardware has been introduced is difficult due to the integration with
existing systems and databases, and also with different organisations.
In terms of operation, the whole workflow process is controlled by business
process management and orchestration software supplied by Staffware, delivered
thin-client through Microsoft IIS on ASP. Staffware’s Process Suite
employs an Independent Process Layer, which enables development of complex
business processes. The workflow tools supplied enable process modelling,
application integration, process monitoring and rapid application development
tools. The software manages the lifecycle of the process from definition,
through deployment, execution, measurement, change and re-deployment.
Reporting services are provided by Crystal Reports. An on-line ‘knowledge
repository’ has been provided alongside the workflow, through ASP
fast-forum, to assist in the capture of informal discussions.
8. Cost savings and productivity improvements
The overall stated objective was to reduce the ownership cost of large
capital assets such as HMS Vanguard, a Trident submarine. The key area
of concern was overhaul times, and specifically the length of time it
took to process enquiries, Surveys & Concessions and other transactions
through the system.
The new process has succeeded in reducing the average
transaction time of SCI’s from 15 days to just seven, a 53 per
cent reduction & Concessions
from 3 months to almost 1 month (29.9) 66.6% reduction (June 2003 – January
2004 -Vanguard). It is recognised that the new system has helped to deliver
and manage 16616 surveys items which would have been extremely difficult
using the paper system.
The overall changes have realised the ambition to
reduce the pre-overhaul enquiry stage. It has also helped to reduce the
Risk to LOP programmes
by increasing visibility of bottlenecks, removed unnecessary administrative
controls and helped the Vanguard Partnership to work more closely.
It
is anticipated that it will be possible to reduce that period further,
as the new workflow system is further refined.
In terms of actual cost
savings, conservative estimates currently predict savings of some £3
million over five years, with the software investment being recovered
within two.
Other benefits have been:
- A significant increase in the accuracy of information
within the system.
- The ability to include more remote parties involved
such as the vessel’s
team and key contractors, such as Rolls Royce. This can help
in supporting engineering and logistics decision making.
- The level
of tracking information has improved dramatically. Every enquiry and
transaction has an audit trail and the project managers
can trace the location of every element of every enquiry, and who or what is
delaying
decisions.
- Management information is available for the first
time. Turnaround times can be evaluated, identifying bottlenecks in
the system.
- Problem solving has been improved. With the spontaneity of
the system, complex problems can be reviewed and resolved in a relatively
short period of time. This is further enhanced by the existence of a discussion
forum
on the system.
- The new workflow system has built in flexibility.
It is scaleable up or down to cope with changes in workload and numbers
of simultaneous
overhaul’s
at different stages.
- A knowledge repository is now available
to all to address future improvements, enabling all parties to mine
the information to understand
where improvements in the associated processes can be made. This will
enable preventative
quality improvements to be made, reducing the cost
of non-quality and directly improving the bottom line.
9. Rollout
The new system is already being used by HMS Talent, HMS Torbay RAMP, HMS
Victorious LOP(R), Trident Class Spares & WSMI areas. This has significantly
expanded the current user base to 731.
Both DML and SubIPT are still learning from the new system, and these
lessons are being implemented. It is anticipated that the efficiency and
cost savings experienced with HMS Vanguard will be exceeded with follow
on platforms benefiting from the already sunk cost.
Published in Supply Chain Practice Vol 6 No,1, March
2004 - produced by the Supply Chain Knowledge Centre, Cranfield Centre
for Logistics & Supply Chain Management, which is part of Cranfield
University School of Management. www.sckc.info
back
|